05.5.1 · Skill in Delivery management

Estimation

Forecasting how long work will take, with honest uncertainty.

Estimates are forecasts, not promises. Ranges and confidence levels are more honest than single numbers. Breaking work down and comparing with past work improves them, and some teams forecast from throughput instead.

Your status · Estimation

Saved in this browser. Sign in to keep it on every device.It colours this skill's tile on your map.

Why it matters for a product engineer

People need to know roughly when work will be done, to plan launches, sales and other work. An estimate is a forecast, not a promise. A product engineer who gives honest ranges, and who can change the scope to fit the time, is more useful than one who gives a precise date that turns out wrong.

How to do it

  1. Give a range and a confidence level, such as “two to four weeks, 85% likely”, not one date.
  2. Break the work down until each piece is understood. The pieces nobody understands are where the time goes.
  3. Compare with similar past work, not with how the work feels today.
  4. Forecast from the team’s real throughput. A Monte Carlo simulation on past delivery gives a range with probabilities.
  5. For a new idea, decide first how much time the problem is worth, then shape a solution that fits.
  6. Update the forecast when you learn something, and say so early.

Common mistakes

  • One number, heard as a promise.
  • Estimating only the coding, not the review, testing and release.
  • Adding pressure to the estimate instead of removing scope.
  • Never checking the old estimates against what happened.

Example

A Basecamp customer asked for a calendar. A full calendar could take six months, so the team asked what six weeks could do. They called the customer and asked when she wanted a calendar. Her office kept bookings for its meeting rooms on a calendar drawn on a wall, and she drove there to check it. The real need was to see free spaces from home, not everything a calendar does.

Side by side

An estimate and an appetite in Shape Up

EstimateAppetite
Starts withA designA number
Ends withA numberA design
What stays fixedThe scopeThe time

With an appetite, the question is not how long the design takes, but which design fits the time the problem is worth.

ReportedRyan Singer, Shape Up, Basecamp

Sources: Set boundaries (Shape Up, chapter 3) ↗ · When can I start telling customers when work will be done? (ProKanban) ↗