Limiting work in progress
Finishing work before starting new work.
Too much work in progress slows everything down and hides problems. Limiting it shortens the time each item takes and makes blockers visible. Stop starting and start finishing.
Why it matters for a product engineer
Every item a team starts and does not finish waits somewhere: in review, in testing, in someone’s head. Too much work in progress makes each item take longer and hides where it is stuck. A limit makes the team finish before it starts, so value reaches users sooner and blockers become visible.
How to do it
- Make all the work visible on one board, including the invisible kind: support, fixes, reviews and meetings that take real time.
- Set a limit for each column. For example, with four pairs of developers, no more than four cards in “In development”.
- When a column is full, help move a card forward before you pull a new one.
- Measure cycle time, from start to done, and throughput, the items finished per week.
- Watch where cards pile up. That column is the bottleneck, and the place to improve.
- Lower the limits slowly, until problems appear, then fix the problems.
Common mistakes
- Limits on paper that nobody respects when a request is urgent.
- Not counting invisible work, so the board looks fine while people are overloaded.
- Limits so high that they never stop anything.
- Measuring how busy people are instead of how fast work finishes.
Example
Siemens Health Services had about 50 teams running 30-day sprints. The last week of each sprint was “a mad rush” to claim points, with hurried testing. Teams started too many features, and most were not finished until the end of the release. The program moved every team to Kanban at once, with WIP limits. The cumulative flow diagram then showed higher throughput in development than in testing across all teams, so management invested heavily in test automation.
How Siemens Health Services changed the way teams took on work
| Sprints | With WIP limits | |
|---|---|---|
| New work starts | At sprint planning | When there is capacity |
| Capacity set by | Story points | WIP limits |
| Measured by | Velocity | Cycle time and throughput |
| The bottleneck | Seen at the release | Seen on the board |
The teams kept their practices. What changed was when work could start, and that made the bottleneck visible.
ReportedBennet Vallet, Siemens Health Services, in InfoQ
Sources: Work in process limits (DORA) ↗ · Kanban at scale: a Siemens success story (InfoQ) ↗