Limiting work in progress

Finishing work before starting new work.

Too much work in progress slows everything down and hides problems. Limiting it shortens the time each item takes and makes blockers visible. Stop starting and start finishing.

Your status · Limiting work in progress

Saved in this browser. Sign in to keep it on every device.It colours this skill's tile on your map.

Why it matters for a product engineer

Every item a team starts and does not finish waits somewhere: in review, in testing, in someone’s head. Too much work in progress makes each item take longer and hides where it is stuck. A limit makes the team finish before it starts, so value reaches users sooner and blockers become visible.

How to do it

  1. Make all the work visible on one board, including the invisible kind: support, fixes, reviews and meetings that take real time.
  2. Set a limit for each column. For example, with four pairs of developers, no more than four cards in “In development”.
  3. When a column is full, help move a card forward before you pull a new one.
  4. Measure cycle time, from start to done, and throughput, the items finished per week.
  5. Watch where cards pile up. That column is the bottleneck, and the place to improve.
  6. Lower the limits slowly, until problems appear, then fix the problems.

Common mistakes

  • Limits on paper that nobody respects when a request is urgent.
  • Not counting invisible work, so the board looks fine while people are overloaded.
  • Limits so high that they never stop anything.
  • Measuring how busy people are instead of how fast work finishes.

Example

Siemens Health Services had about 50 teams running 30-day sprints. The last week of each sprint was “a mad rush” to claim points, with hurried testing. Teams started too many features, and most were not finished until the end of the release. The program moved every team to Kanban at once, with WIP limits. The cumulative flow diagram then showed higher throughput in development than in testing across all teams, so management invested heavily in test automation.

Side by side

How Siemens Health Services changed the way teams took on work

SprintsWith WIP limits
New work startsAt sprint planningWhen there is capacity
Capacity set byStory pointsWIP limits
Measured byVelocityCycle time and throughput
The bottleneckSeen at the releaseSeen on the board

The teams kept their practices. What changed was when work could start, and that made the bottleneck visible.

ReportedBennet Vallet, Siemens Health Services, in InfoQ

Sources: Work in process limits (DORA) ↗ · Kanban at scale: a Siemens success story (InfoQ) ↗

Resources

1
  • docsStart here
    Work in process limits ↗
    DORA (Google Cloud) · 5 min

    How limiting work in progress shortens lead time and makes bottlenecks visible.