Cost of delay estimates the value lost each week a piece of work is not done. Some work loses value fast, like a seasonal feature, and some can wait. It is a strong argument for doing small, urgent things before big, comfortable ones.
Why it matters for a product engineer
Every week a valuable feature waits in a queue, its value is lost and does not come back. Cost of delay puts a number on that loss. It changes the discussion from “what is the cheapest work?” to “what is the most expensive to leave waiting?”. It is a strong argument for small, urgent work before big, comfortable work.
How to do it
- For each piece of work, estimate the value per week once it is live: revenue, savings, risk avoided.
- Ask how that value changes with time. Some work loses value fast, such as a seasonal feature or a deadline. Some can wait.
- Estimate how long the work takes.
- Divide cost of delay by duration. The result is often called CD3. Do the work with the highest number first.
- Measure the time work spends waiting, not only the time it is in progress.
- Use rough numbers. The order matters more than the precision.
Common mistakes
- Prioritising by effort alone, so big valuable work waits for ever.
- Ignoring the time work waits before anyone starts.
- Starting everything at once, so everything is delayed.
- Treating every request as urgent, so the method means nothing.
Example
At Maersk Line, Joshua Arnold and Özlem Yüce applied cost of delay to a $100 million portfolio of software work. Before, requirements took 150 days on average from idea to production. They traced one real feature: its cost of delay was about $210,000 a week, and it had waited 38 weeks in queues. That waiting alone cost nearly $8 million.
One Maersk Line feature, and the price of its wait
- $210k
- Cost of delay per week
- 38weeks
- Waiting in queues
- ~$8M
- Value lost while it waited
Most of the loss came from waiting, not from building. A number per week makes that visible.
ReportedJoshua Arnold and Özlem Yüce, Maersk Line experience report, presented at Agile2013
Sources: Black Swan Farming using Cost of Delay (Joshua Arnold and Özlem Yüce) ↗
Resources
3- articleStart here
Cost of delay ↗
Joshua Arnold (Black Swan Farming) · 4 minWhat it costs to do something later, and why it should drive priority more than effort does.
- articleStart here
Qualitative cost of delay ↗
Black Swan Farming · 11 minA lighter version for teams that cannot put money figures on every idea.
- articleGo deeper
Cost of delay and CD3 prioritisation at scale ↗
Joshua Arnold (Black Swan Farming) · 9 minDividing cost of delay by duration to order work, as applied across a large portfolio.