Cognitive biases

Systematic errors in thinking, such as confirmation bias.

Confirmation bias, sunk cost, anchoring and the curse of knowledge all distort product decisions. Knowing them does not make you immune, but it helps you design processes that catch them, such as writing predictions down first.

Your status · Cognitive biases

Saved in this browser. Sign in to keep it on every device.It colours this skill's tile on your map.

Why it matters for a product engineer

Some errors in thinking are not random. They push in the same direction again and again. We notice evidence that agrees with us (confirmation bias). We keep funding a project because of what it already cost (sunk cost). We stay close to the first number we hear (anchoring). We plan as if our project will go better than similar ones (the planning fallacy). Knowing these names does not protect you. A process that checks your thinking at the right moment does.

How to do it

  1. Write down your prediction before you see the results of a test or a launch.
  2. Before you estimate, look at how long similar projects really took, then adjust from there.
  3. Ask what evidence would change your mind, and look for it on purpose.
  4. When you decide whether to continue a project, ignore what it has already cost.
  5. Ask someone with no stake in the idea to argue against it.

Common mistakes

  • Thinking that knowing about biases makes you free of them.
  • Looking only at the average result of past projects, not the worst ones.
  • Reading user research only for quotes that support the plan.
  • Calling it “commitment” when it is sunk cost.

Example

In 2003, Levi Strauss started moving to a single SAP system, with a budget of less than $5 million. In 2008, it took a $192.5 million charge for the project. Researchers at Oxford studied 1,471 IT projects. The average cost overrun was 27%, but one project in six overran by 200% on average. They recommend reference class forecasting, a method based on the work of Kahneman and Tversky: estimate from the results of similar projects, not from your own plan.

Numbers

Cost and schedule overruns in 1,471 IT projects

27%
Average cost overrun
1 in 6
Projects with an extreme overrun
200%
Their average cost overrun
~70%
Their average schedule overrun

The average looks manageable. The risk is in the tail, which an optimistic plan does not include.

ReportedFlyvbjerg and Budzier, Harvard Business Review, September 2011

Sources: Why your IT project may be riskier than you think (Flyvbjerg and Budzier, Harvard Business Review, 2011; author copy) ↗ · Confirmation bias in UX (NN/g) ↗ · Confirmation bias and the power of disconfirming evidence (Farnam Street) ↗